MIGRATION TO NEW DCS & SIS FOR PVCII

Client:• PEQUIVEN Consignee and Delivery:• PVC2 PVC2 Project Data:• Initial date: April-2015• Finish date: October-2015 Work Performed:• Engineering to implement the PVC2 original plant production. Hardware and software to complete migration to a new Yokogawa DCS and SIS Controllers. Logistic, procurement and installation of controllers, I/O cards, stations, panel, cabinets and servers.• FAT & SAT […]